Document Type: Turn Over Docs
Project Name: SRPC/O&M-PR-2088 Supply of design, Engineering, Installation and testing for the Enhancement of Facilities Maintenance Management System to incorporate Hot Server Backup with redundancy, Including restoration of one workstation.
Account Manager: Deng Silorio
Project Manager: Meric B. Mara
Technical Team:
Eman Calso
Rodel Hipolito
Clients Name: San Roque Power Corporation
Industry: Power Plant
Contact Person: Marcel Ablog
Designation: Systems Engineer
Email Address: marcel15@mozcom.com
Telephone Number: (63) 2 886-5300
Fax : (63) 2 886-5310
URL: http://www.sanroquedam.ph
Delivery- Server Solution Components
Server Component | Status/ Percentage of Completion | Remarks |
| Delivered | As of August 4, 2006 |
| Delivered | As of August 4, 2006 |
Total Project Completion Rate: 100%