Friday, August 04, 2006

SRPC PROJECT COMPLETED:100%

Document Type: Turn Over Docs

Project Name: SRPC/O&M-PR-2088 Supply of design, Engineering, Installation and testing for the Enhancement of Facilities Maintenance Management System to incorporate Hot Server Backup with redundancy, Including restoration of one workstation.

Project Code: 8L-SRPC02

Account Manager: Deng Silorio

Project Manager: Meric B. Mara

Technical Team: Allan Andal

Eman Calso

Rodel Hipolito

Clients Name: San Roque Power Corporation

Industry: Power Plant

Contact Person: Marcel Ablog

Designation: Systems Engineer

Email Address: marcel15@mozcom.com

Telephone Number: (63) 2 886-5300
Fax : (63) 2 886-5310

URL: http://www.sanroquedam.ph

Delivery- Server Solution Components

Server Component

Status/ Percentage of Completion

Remarks

  • Project Turn Over

Delivered

As of August 4, 2006

  • CD Installer

Delivered

As of August 4, 2006


Total Project Completion Rate: 100%